Due to the milder weather, the Water Conditioning Project was able to resume and is currently 90% complete.
This week, we received the soda ash injection system, which will be installed over the coming weeks. Final finishing touches still need to be done to the wellhouse structure, once the injection system has been installed.
Following the installation of the soda ash system, Public Works will slowly be adding soda ash to the water system to bring up the water's pH, making it less corrosive. Once the system is operational, the results will not be instantaneous, adjustments to the system will be required for a period of time to stabilize the pH levels.
The Village will advise once we begin adding soda ash to the system.
Questions? Contact Tim Harris, Manager of Operations & Development Services at 604.894.6135 x 240 or tharris@pemberton.ca.